Опыт

OIRFP Prirazlomnaya

Date
From 2009 to the present

Completion: %

TECHNOLOGICAL FACILITIES
  • Facilities of the drilling complex;
  • General platform systems;
  • Energy complex;
  • Technological complex;
  • APCS;
  • Ventilation system;
  • Gas turbine generators.
TYPES OF WORK
  • Installation of automation systems;
  • Commissioning of electrical equipment;
  • Commissioning of automation systems;
  • Commissioning of technological and mechanical equipment;
  • Provision of services for the verification and calibration of measuring instruments;
  • Keeping a duty-watch service for the maintenance of electrical equipment;
  • Maintenance and support in the operation of HVAC systems;
  • Established delivery of materials by sea from the cities of Arkhangelsk and Murmansk.

 

 

Customer
Gazpromneft-Shelf OJSC

See feedback

Arctic LNG 2 Project

Date
From 01.02.2021 to the present

Completion: %

TECHNOLOGICAL FACILITIES
3 process lines of a fully prefabricated assembly consisting of:
  • GBS with LNG and SGC storage facilities;
  • Topsides with technological modules, loading arms and energy supply facilities.
 
Onshore facilities:
  • Main (flare system, operational control complex, pipeline racks);
  • Auxiliary (boiler room, utility infrastructure facilities).

 

TYPES OF WORK
  • Construction and installation work;
  • Electrical works;
  • Installation of automation and telecommunication systems;
  • Commissioning of electrical equipment, automation systems;
  • Operation and maintenance of gas supply facilities of the "NOVATEK-Murmansk" plant.

 

 

Customer
Arctic LNG 2 LLC

See feedback

Astrakhansky GPP

Date
2013 - 2015

Completion: 100%

TECHNOLOGICAL FACILITIES
  • Expansion of production facilities No. 3,6 for processing gas condensate at the Astrakhansky GPP. Pentane-hexane fraction isomerization unit
  • Expansion of production facilities No. 3,6 for processing gas condensate at the Astrakhansky GPP. Flare header for low-pressure acid gases of the 1st and 2nd stages at the Astrakhansky GPP. Automated control system (FOCL)
  • Reconstruction of stock and raw material parks of production facility No. 6 at the Astrakhansky GPP. Liquified Gas Warehouse SUG-2(U505)
  • Expansion of production facilities No. 3,6 for processing gas condensate at the Astrakhansky GPP. Gas condensate processing combined unit. CDU block. Stage 2
  • Off-site communication and signaling networks. Boiler house. Reverse osmosis unit for preliminary desalination. Steam condensate purification unit

 

TYPES OF WORK

Installation and commissioning works

 

Customer
Gazprom Invest Yug JSC

See feedback

Expansion of polyethylenerefhtalate production up to 210000 tons per year

Date
2013

Completion: 100%

TECHNOLOGICAL FACILITIES

СР1, СР2

  • Pneumatic conveyor system of  purified terephthalic acid of polyethyleneterephthalate production CP1 and CP2  
  • Silage output line
  • Isopropyl-N-phenylcarbamate feed system for CP1 and CP2
  • Modification of suspension  unit
  • Modification of suspension consumption tank  
  • Modification of esterifier system
  • Esterifier separation column  
  • Modification of oligomer line  
  • Pre-polycondenser system  
  • Pre-polycondenser preheater
  • Polycondenser circulation system
  • Heat exchangers cleaning system
  • Pre-polycondenser circulation system  
  • Installation of glycol ejectors  
  • Granulation system and granules conveyor system, polymer melt conduit  


SSP2

  • Hot dedusting and pre-crystallization unit
  • Nitrogen purification unit
  • Hot crystallization unit
  • Solid-phase polycondensation unit
  • Product cooling unit
  • Heating-distribution system
  • Heating-transfer system
  • Silage tank piping system


UNIT  302

  • Polyethyleneterephthalate silage tanks

 

TYPES OF WORK

Commissioning, start-up

 

Customer
POLIEF OJSC

See feedback

Yurubcheno-Tokhomskoe Oil Field

Date
From 2015 to the present

Completion: 100%

TECHNOLOGICAL FACILITIES
  • Oil treatment plant;
  • Adding of reservoir park;
  • Transfer and acceptance point;
  • Power building;
  • Camp;
  • Administration and living quarters;
  • Gas compressor station
  • Fire station;
  • Substation 35/6 kV;
  • Plant power station 48 mW;
  • Fuel and lubricant warehouse with centralized helicopters fuelling system;
  • Oil and gas gathering lines;
  • Oil and gas production unit.
TYPES OF WORK
  • Installation of electrical equipment;
  • Installation of automation systems;
  • Commissioning of electrical equipment;
  • Commissioning of automation systems;
  • Commissioning of process and mechanical equipment;
  • Metrological support of measuring instruments.

Customer
Vostsibneftegaz JSC

See feedback

Деятельность

Installation and commissioning of electrical equipment
Installation and commissioning of instrumentation, process control, security, fire alarm, CCTV and communication systems
Engineering
​Process, equipment, and engineering systems commissioning
Maintenance services
Verification and calibration of measuring instruments
Installation and adjustment of heating, ventilation and air conditioning (HVAC) systems
Construction and mechanical installation
Development and assembling of training stands