Date
2013 - 2021
Completion: 100%
Carrying out construction and installation works at the facilities for the "Arrangement of sites for single wells and cluster sites of oil fields named after R. Trebs. First priority"; "Arrangement of sites for single wells and cluster sites of oil fields named after R. Trebs. Field support site. First priority"
Arrangement of oil fields named after R.Trebs and A.Titov. Oil pre-gathering site. Varandey
Formation of operational documentation for the facilities at the R. Trebs field
Range of commissioning works “under load” at the facilities of the 1st priority of the 1st stage at the R.Trebs deposit
Date
From 2009 to the present
Completion: %
Date
2013 - 2015
Completion: 100%
Installation and commissioning works
Date
2013 — 2014
Completion: 100%
GF-2 UNIT
Ethane-propane fraction separation unit
Isobutane-butane fraction separation unit;
Flare system;
Steam condensate transfer and hot water treatment unit ;
Methanol feed unit to process pipelines of finished products;
RAW MATERIAL BASE YUZHNAYA
Tank farm;
Pump house;
Flare;
Loading/unloading rack;
Vapor recovery system
RAW MATERIAL BASE SEVERNAYA
Tank farm;
Pump house;
Flare;
Loading/unloading rack;
Refrigeration unit;
Antifreeze heating unit;
NGL transfer unit
AESEOTROPIC DISTILLATION AND PROPANE FRACTION METHANOL REMOVAL UNIT
Propane fraction methanol removal unit:
Propane fraction methanol extraction unit
Propane fraction azeotropic dehydration unit
Methanol recovery unit
Commissioning, start-up
Date
From 2015 to the present
Completion: 100%