Опыт

Kapitonovskoye and Tsarichanskoye deposits, Orenburg region

Date
2013 - 2017

Completion: 100%

TECHNOLOGICAL FACILITIES
AEK
Oil and gas treatment unit
TYPES OF WORK
  • Construction and installation works
  • Commissioning works
  • Range of services for the maintenance of measuring units for the wellstream and ensuring measurement at production wells
  • Comprehensive testing on the operational products

Customer
Gazprom Neft Orenburg CJSC

See feedback

Arctic LNG 2 Project

Date
From 01.02.2021 to the present

Completion: %

TECHNOLOGICAL FACILITIES
3 process lines of a fully prefabricated assembly consisting of:
  • GBS with LNG and SGC storage facilities;
  • Topsides with technological modules, loading arms and energy supply facilities.
 
Onshore facilities:
  • Main (flare system, operational control complex, pipeline racks);
  • Auxiliary (boiler room, utility infrastructure facilities).

 

TYPES OF WORK
  • Construction and installation work;
  • Electrical works;
  • Installation of automation and telecommunication systems;
  • Commissioning of electrical equipment, automation systems;
  • Operation and maintenance of gas supply facilities of the "NOVATEK-Murmansk" plant.

 

 

Customer
Arctic LNG 2 LLC

See feedback

Astrakhansky GPP

Date
2013 - 2015

Completion: 100%

TECHNOLOGICAL FACILITIES
  • Expansion of production facilities No. 3,6 for processing gas condensate at the Astrakhansky GPP. Pentane-hexane fraction isomerization unit
  • Expansion of production facilities No. 3,6 for processing gas condensate at the Astrakhansky GPP. Flare header for low-pressure acid gases of the 1st and 2nd stages at the Astrakhansky GPP. Automated control system (FOCL)
  • Reconstruction of stock and raw material parks of production facility No. 6 at the Astrakhansky GPP. Liquified Gas Warehouse SUG-2(U505)
  • Expansion of production facilities No. 3,6 for processing gas condensate at the Astrakhansky GPP. Gas condensate processing combined unit. CDU block. Stage 2
  • Off-site communication and signaling networks. Boiler house. Reverse osmosis unit for preliminary desalination. Steam condensate purification unit

 

TYPES OF WORK

Installation and commissioning works

 

Customer
Gazprom Invest Yug JSC

See feedback

Plant of "Sibur-Khimprom"

Date
From August 2020 to the present

Completion: %

TECHNOLOGICAL FACILITIES

Plant facilities

TYPES OF WORK
  • Repair of reciprocating compressors;
  • Maintenance and preventive maintenance of ventilation equipment, fans and electric motors of air cooling devices, cooling towers, smoke exhausters. Cleaning, repairing, manufacturing, replacing of air ducts, dampers, valves, soft inserts, grounding based on the actual technical state;
  • Performing service works on the repair of technological equipment and works within the framework of shutdown repairs;
  • Elimination of leaks on technological equipment.

Customer
Sibur-Khimprom JSC

See feedback

Yurubcheno-Tokhomskoe Oil Field

Date
From 2015 to the present

Completion: 100%

TECHNOLOGICAL FACILITIES
  • Oil treatment plant;
  • Adding of reservoir park;
  • Transfer and acceptance point;
  • Power building;
  • Camp;
  • Administration and living quarters;
  • Gas compressor station
  • Fire station;
  • Substation 35/6 kV;
  • Plant power station 48 mW;
  • Fuel and lubricant warehouse with centralized helicopters fuelling system;
  • Oil and gas gathering lines;
  • Oil and gas production unit.
TYPES OF WORK
  • Installation of electrical equipment;
  • Installation of automation systems;
  • Commissioning of electrical equipment;
  • Commissioning of automation systems;
  • Commissioning of process and mechanical equipment;
  • Metrological support of measuring instruments.

Customer
Vostsibneftegaz JSC

See feedback

Деятельность

Installation and commissioning of electrical equipment
Installation and commissioning of instrumentation, process control, security, fire alarm, CCTV and communication systems
Engineering
​Process, equipment, and engineering systems commissioning
Maintenance services
Verification and calibration of measuring instruments
Installation and adjustment of heating, ventilation and air conditioning (HVAC) systems
Construction and mechanical installation
Development and assembling of training stands